    Auren Energia sells R$351m of power to Brazilian distributors in the A-1 existing energy auction

    Auren Energia sold 1.23m MWh at R$286/MWh in Brazil's 13 November A-1 existing energy auction, contracts worth R$351.2m (about $62m) for supply in 2027 and 2028.

    ClimateTech Navigator · 23 November 2026 · 2 minute read

    Brazilian renewable generator Auren Energia sold 1,228,080 MWh of electricity to regulated distribution companies in the A-1 existing energy auction held on 13 November 2026, according to the CCEE results sheet. Auren contracted 700 lots at R$286.00/MWh, against an opening price of R$290.00/MWh, for a total of R$351,230,880, about $62.1m at the closing exchange rate on the day of the auction.

    The national electricity regulator ANEEL and the electricity trading chamber CCEE ran three existing energy auctions that day, A-1, A-2 and A-3, under guidelines from the Ministry of Mines and Energy. Energy bought in the A-1 auction will be delivered between 1 January 2027 and 31 December 2028, Agência Gov reported. The A-1 auction cleared at an average of R$286.35/MWh, a discount of 1.26% to the R$290.00/MWh ceiling, and contracted 2,485 average MW, or 43,596,840 MWh, worth about R$12.48bn. The government agency put the saving for Brazilian consumers from that discount at about R$159m.

    Across all three auctions, the CCEE results show R$14.25bn of contracts covering 50.17m MWh, with 47 winning sellers and an average price of R$284.04/MWh, a discount of 1.15%. Canal Solar reported that the A-1 auction had 46 sellers, among them Auren, Axia Energia, Casa dos Ventos, Cesp, Engie, Rio Energy, BTG Pactual, Copel and Enel. Auren's sale sat at R$286.00/MWh, slightly below the A-1 average, and its 700 lots made it one of the larger sellers on the results sheet alongside BTG Pactual Sertrading, which sold 2,500 lots.

    The climate case

    Auren generates only renewable power, from 8.7 GW of installed capacity split 54% hydro, 36% wind and 10% solar, according to company presentations summarised by Quartr, which makes it Brazil's third-largest generator. This sale comes from existing plants for delivery in 2027 and 2028, so it keeps renewable output under contract rather than adding new capacity.

    Brazil already got 89% of its electricity from low-carbon sources in 2025, according to Ember, so the distributors buying this power draw on a grid that is mostly clean. The bigger climate problem in Brazil is wasted output, after the country curtailed about a fifth of its wind and solar generation in 2025, according to a Volt Robotics report covered by pv magazine, which blamed grid constraints and mismatches with demand. An existing-energy auction contract does not address that bottleneck.

    How it fits the data

    ClimateTech Navigator has one earlier commercial deal on record for Auren this year, a power purchase agreement with data centre operator Equinix in March 2026, for which no value was disclosed. Including this sale, it has tracked four power purchase agreements dated 2026 for Brazilian companies, with $297m of disclosed value between them.

    Sources: Quartr summary of Auren presentation, Ember Brazil, pv magazine, CCEE auction results, 13 November 2026; Agência Gov, 13 November 2026; Canal Solar, 13 November 2026. Company profile

    The ClimateTech Navigator platform

    The full database behind every story

    Every company, investor, deal, fund, patent and paper, linked and searchable. Ask the Assistant, set alerts, or connect it to your own AI tools.

    The ClimateTech Navigator platform dashboard

    Related reading